Sidewalk Replacement on County Road 2 Begins This July
The Township of Edwardsburgh Cardinal is replacing the asphalt sidewalk along County Road 2 in Cardinal this month, starting east from St. Lawrence Street.
Construction Schedule
- Early July: Lloyd McMillan Equipment Ltd. will begin removing the existing sidewalk.
- Week of July 22: Black Tar Construction will install the new asphalt surface (weather permitting).
What to Expect
- Please avoid parking on or near the sidewalk path during construction.
- Driveway transitions will be smoothed, and lawn areas will be restored in August.
- If possible, avoid driving over the new sidewalk for 24 hours after paving.
Note on Private Driveways
This project does not include private driveways. However, residents interested in having driveway work done can contact Black Tar Construction at 888-424-5455 or bookings@blacktar.ca.
We appreciate your patience as we complete this improvement. If you have questions, please contact David Grant, Director of Operations, at 613-658-3001 x5 or dsgrant@twpec.ca.
Read the full Letter to Residents